A construction project to modernize part of Cyprus’ local government system has come under fire after the Auditor General revealed several irregularities, from bypassing public tenders to starting work without building permits or signed contracts.
The issue concerns a contract of around 1.5 million-euro contract awarded directly (without a tender) for renovations at the former Nicosia Water Supply Council (SYL) building. The project was part of a wider effort to accommodate the Development Licensing Directorate under newly restructured local government bodies.
But, according to a damning report from the Auditor General, rules were bent and in some cases, outright ignored, to push the project through quickly.
The report reveals that the contractor started construction well before securing the required town planning and building permits. In fact, the permit application was only filed in April 2024, nearly a month after renovation work had already begun. Not only were the rules sidestepped, but the building was already in use before the necessary approvals had even been submitted.
Perhaps even more concerning is that work began before the project was formally approved or a contract signed.