There may be a strong investment interest expressed in the creation of data centers in Greece, but the capacity of the national grid to support such large investments is under careful evaluation. This is the snapshot of the situation regarding data center projects, which are considered essential for the technological development of the country.
Demand for computing power is projected to grow globally three to five times over the next decade, due to the increased use of artificial intelligence applications. A few years ago, the users of such applications did not exceed 100 million, while today they reach 1.5 billion.
This increase is made possible thanks to significant developments in processors, which create the need for larger data centers, capable of supporting increased computing power. As a result, the average size of a data center is expected to increase tenfold over the next decade.
That is expected to create prospects for 5 gigawatt installations in Southeastern Europe, where Greece could claim a key role. This is a process that has already begun, as interest has been expressed in this country for up to 2.2 GW, based on the requests that have been made to the two network operators, DEDDIE and ADMIE, as reported by a PwC study on the location of data centers in Greece, at the initiative of the Digital Governance Ministry.
Already, 16 connection requests have currently been submitted to the DEDDIE distribution network and approximately 20 to ADMIE. Of these, approximately 30% have already received connection terms, which indicates that part of the investment projects is already at a more mature stage.
Nevertheless, the large volume of investments, approximately 65%, is concentrated in Attica and the remaining percentage is mainly distributed in Crete, Viotia and Corinth. This concentration tests the resilience of Attica’s electrical system, at the same time as the available power remains limited to cover the energy needs of new projects.
Based on current data, it is estimated that 300 to 700 MW of power from the planned data centers may face difficulties in connecting to the Attica network. This makes it necessary to geographically redirect part of the investments to areas where there is available electrical power.