Clouds are thickening again over the Crete-Cyprus electricity interconnection (GSI), as a regulatory impasse returns with growing urgency – just six months after a Greece-Cyprus intergovernmental agreement had appeared to resolve it. Pressure is mounting ahead of a crucial August deadline for payments to French cable manufacturer Nexans.
The stakeholders – including Nexans, the regulatory authorities of Greece (RAAEY) and Cyprus (CERA), the European Commission, which has approved €657 million in funding for the project, and ADMIE, which is the project’s implementing body – have been locked in intensive talks in recent weeks in an effort to break the deadlock. But prospects appear dim, as none of the parties seem to hold much confidence in a solution.
Concerns over the financial fallout dominated a fruitless videoconference chaired by the European Commission on Tuesday – the second in a week – with a third now scheduled for next Wednesday, July 23.
During Tuesday’s meeting, ADMIE reportedly urged CERA not to impose a €25 million annual cap on the recovery of construction costs in its forthcoming decision. But the Cypriot regulator refused, citing the Greece-Cyprus agreement, which explicitly includes a cost-recovery ceiling.
In response to EU objections – namely, that such a ceiling is not permitted under the European regulatory framework – CERA argued that the GSI project is not progressing through all its planned phases or according to its construction schedule. The regulator reportedly pointed to delays in key seabed surveys, implying that the project does not meet the criteria of a standard interconnection.